General Aviation’s importance to users and to RST’s success has spurred plans to upgrade and expand the existing GA ramp. This is being done to replace existing aged infrastructure and to provide additional aircraft parking and includes:
The project will be funded by FAA Bipartisan Infrastructure Law, MNDOT Aeronautics, and airport reserve funds and is expected to begin this summer. Check back to this page for news and updates regarding the construction and impacts to our general aviation community.
Work Area 3 began on August 26th. Shown in dark gray and blue in the image, Work Areas 3A and 3B are estimated to span 9 to 11 weeks and will wrap up our 2026 construction efforts. These work areas include construction of concrete parking pads and reconstruction of apron pavement to the east of Work Area 2 along with fencing modifications and infrastructure installation for two new high-speed gates. However, the new gates will not be active until 2027 following the completion of underground utility work.
View the details of the phased work plan here.
Work area 3C, the T-hangar taxilane resurfacing, has been delayed and will not occur until Spring 2027.
We will continue to update our GA community as the timing is solidified. The variability in predicting construction events affected by weather or other unforeseen conditions makes it difficult to pinpoint exact dates. Thank you for your patience as we complete these needed improvements. Questions are invited and encouraged. For urgent matters, please call Mead & Hunt’s Construction Manager at 507.738.0871. Non-urgent questions about the project may be submitted using the button below.
Paving is currently occurring in Work Area 2 and is anticipated to be completed by August 25th. This marks the final work associated with Work Area 2, which is anticipated to reopen to aircraft traffic by August 28th, subject to weather delays and any unforeseen events. The contractor is expected to begin work in Work Area 3 on August 26th. Work Area 3 (shown in dark gray and blue) is estimated to span 8 to 10 weeks and includes construction of concrete parking pads and reconstruction of apron pavement to the east of Work Area 2, the addition of a new vehicle access road with high-speed gates, utility installation, and the mill and overlay of the T-hangar pavement.
View the details of the phased work plan here.
T-hangar taxilane resurfacing has been delayed and will not occur until late September, at the earliest. We will continue to update our GA community as the timing is solidified.
The variability in predicting construction events affected by weather or other unforeseen conditions makes it difficult to pinpoint exact dates. Thank you for your patience as we complete these needed improvements.
Questions are invited and encouraged. For urgent matters, please call Mead & Hunt’s Construction Manager at 507.738.0871. Non-urgent questions about the project may be submitted using the button below.
The contractor is currently installing storm drain in Work Area 2. As noted previously, reconstructed Taxiway K and all of Work Area 1 are now open to aircraft traffic. Taxiway K can be accessed from Taxilane 3 as seen in this screenshot. Punchlist work will occur periodically on or around this newly paved surface. During Work Area 2, Signature Aviation will park aircraft in Work Area 1 (shown in light gray).
View the details of the phased work plan here.
Work Area 2 paving is currently expected to begin around August 20th, though could be delayed due to weather or other unforeseen factors. Taxiway J (shown in orange) has been permanently removed.
Work Area 2 is anticipated to be reopened the week of August 24th, subject to weather delays and any unforeseen events.
T-hangar taxilane resurfacing (Work Area 3) is now anticipated for mid-September.
The variability in predicting construction events affected by weather makes it difficult to pinpoint exact dates. Thank you for your patience as we complete these needed improvements.
Questions are invited and encouraged. For urgent matters, please call Mead & Hunt’s Construction Manager at 507.738.0871. Non-urgent questions about the project may be submitted using the button below.
The contractor is currently installing storm drain in Work Area 2. As noted previously, reconstructed Taxiway K and all of Work Area 1 are now open to aircraft traffic. Taxiway K can be accessed from Taxilane 3 as seen in this screenshot. Punchlist work will occur periodically on or around this newly paved surface. During Work Area 2, Signature Aviation will park aircraft in Work Area 1 (shown in light gray).
The contractor has completed paving in Work Area 1. The reconstructed Taxiway K and all of Work Area 1 are open to aircraft traffic. Taxiway K can be accessed from Taxilane 3 as seen in this screenshot. Punchlist work will occur periodically on or around this newly paved surface.
On July 8, the contractor began construction in Work Area 2, which comprises the central portion of the apron (shown in dark gray and orange). This involves removing existing asphalt surface, installing additional storm drain, reconstructing and expanding the apron pavement toward Taxiway A, and some grading south of the apron. Taxiway J (shown in orange) is now permanently closed and will be removed during this phase of the project. Twenty-five (25) working days (5-6 weeks) are anticipated for Work Area 2, subject to weather delays and any unforeseen events. During this time, Signature Aviation will park aircraft in Work Area 1 (shown in light gray).
T-hangar taxilane resurfacing (Work Area 3) is still anticipated for mid-August.
Base rock for paving the current apron work area was completed in mid-June. A test strip of asphalt was placed on June 22nd and approved on June 24, 2026. Paving will continue for an additional 3-5 days. The contractor will continue to haul asphalt on Taxilane 3 (just north of the apron’s west edge). The contractor and paving company will yield to and move out of the way of aircraft traffic on the taxilanes during this process. The schedule of this work is entirely weather dependent. Contractor crews continue to maintain the site and restore disturbed areas to keep conditions stable and safe.
View the details of the phased work plan here.
On June 15th a new phase of work began at Taxiway K, which required the closure of Taxiway A between A7 and A8 for 10 days, weather permitting. Taxiway A is scheduled to reopen the afternoon of June 25th.
Due to the delays in Work Area 1, the T-hangar taxilane resurfacing initially anticipated for July will be delayed. At this time, the best-case scenario earliest timeframe in which that work would begin is mid-August.
The variability in predicting construction events affected by weather makes it difficult to pinpoint exact dates. Thank you for your patience as we complete these needed improvements.
Questions are invited and encouraged. For urgent matters, please call Mead & Hunt’s Construction Manager at 507-738-0871. Non-urgent questions about the project may be submitted using this form.
A portion of Taxiway A will be closed to aircraft traffic for a 10-day period beginning Monday, June 15th at 7:00 a.m. Taxiway A is expected to reopen by 11:00 p.m. on Wednesday, June 24th. As always, this work is weather-dependent, and it is possible the reopening could be delayed. During this time, the alternate taxi route is for aircraft taxiing from the west to exit Taxiway A onto Taxiway A8, back-taxi on Runway 13/31, then use Taxiway A7 to rejoin Taxiway A. Taxiways J and H can be used to access the GA ramp. Pilots should confirm and coordinate taxi routes with the air traffic control tower. This closure is necessary to complete the reconstruction of Taxiway K where it connects to Taxiway A.
Additionally, the test strip paving for the west portion of the GA ramp is currently scheduled for Tuesday, June 16th (weather-dependent). Please see the June 5th update below for more information on what to expect during this first phase of paving.
RST is committed to keeping our GA community as up to date as possible. Thank you for your patience as we complete these needed improvements.
Questions are invited and encouraged. For urgent matters, please call Mead & Hunt’s Construction Manager at 507-738-0871. Non-urgent questions about the project may be submitted using this form.
In mid-April, limestone rock was discovered below the old apron (Work Area 1C) and to the west (Work Area 1B) where new storm drains are being constructed. The contractor spent a few weeks in April and early May removing the rock, resulting in slower than expected excavation and adding time to the schedule. In late May, the new storm drains under the apron were completed and base rock installation began on June 1st.
View the details of the phased work plan here.
During the next portion of work, the contractor will be hauling asphalt on Taxilane 3 (just north of the apron’s west edge). The contractor and paving company will yield to and move out of the way of aircraft traffic on the taxilanes during this process. This work is entirely weather dependent, but may start as early as June 15th. When this eventually occurs, there will be a single day of paving for the test strip. There is a delay of at least a day after paving the test strip, then they will pave 3-5 days in a row. If rain is encountered, the first day of paving could be delayed. In the meantime, crews are maintaining the site and restoring disturbed areas to keep conditions stable and safe.
The variability in predicting construction events affected by weather makes it difficult to pinpoint exact dates. Thank you for understanding.
Work Area 1 begins April 13 and includes west apron construction and closure of Taxiway K.
The information shared at the GA Community Meeting on March 26 at 5:30 p.m. in the Signature Hangar is available here.
The presentation included the proposed schedule and project phasing information. Construction is anticipated to begin in early April, weather permitting, and end in November.
Work is picking back up on the GA ramp project. Last month, crews demolished the old T-hangar near the GA ramp to make way for future hangar and infrastructure development. Crews also completed installation of new DarkSky-compliant LED apron light fixtures on the cargo and GA aprons. This lighting upgrade is more energy-efficient and directs more of the light down onto the ramp where it is most needed, reducing unnecessary light pollution.
Federal and state grant funding for the GA Ramp Expansion project was secured in mid-September. Due to the unpredictability of fall weather, the contractor intends to move forward with limited construction activities this fall. Users can expect to see improvements to the GA ramp lighting with the conversion of the existing lighting to LED lighting this fall or winter. No pavement reconstruction will occur this fall. The remainder of the reconstruction and expansion work is expected to begin in April or May 2026. Users can expect to receive notification of a user meeting in the spring where the project team will share project phasing details, anticipated closure schedules, alternate routes to and from impacted areas, and ways to keep up to date on the latest developments. Check back to this webpage often as RST will provide updates throughout the project!
RST and its design and construction partners are excited to begin work on the GA Ramp Expansion project. Although later than originally expected, federal and state grant funding is anticipated to be secured by the end of September 2025.
Once the funding is available, the contractor intends to move forward with limited construction activities this fall, such as earthwork, grading, drainage, apron lighting upgrades, and pipe installation. No pavement reconstruction will occur this fall, with the majority of the reconstruction and expansion work taking place in 2026.
Project phasing will be shared as soon as a detailed schedule is known.
Update your contact information to receive updates regarding the project.
Updated: January 2026.
Rochester International Airport (RST) strives to ensure that its services are accessible to people with disabilities. Rochester International Airport (RST) has invested a significant amount of resources to help ensure that its website is made easier to use and more accessible for people with disabilities, with the strong belief that every person has the right to live with dignity, equality, comfort, and independence.
The Web Content Accessibility Guidelines (WCAG) defines requirements for designers and developers to improve accessibility for people with disabilities. It defines three levels of conformance: Level A, Level AA, and Level AAA.
Rochester International Airport (RST) is making constant efforts to improve the accessibility of its site and services in the belief that it is our collective moral obligation to allow seamless, accessible, and unhindered use for those of us with disabilities.
We aim to make all pages and content on flyrst.com accessible, but some content may not yet fully meet the highest accessibility standards. This could be due to challenges in identifying the most suitable technological solution.
We may revise this Statement periodically to reflect improvements or changes to our accessibility practices.
The Flyrst.com accessibility menu can be enabled either by hitting the tab key when the page first loads or by clicking the accessibility menu icon that appears in the corner of the page. After triggering the accessibility menu, please wait a moment for the accessibility menu to load in its entirety.
If you are experiencing difficulty with any content on Flyrst.com or require assistance with any part of our site, please contact us during normal business hours as detailed below, and we will be happy to assist.
If you wish to report an accessibility issue, have any questions, or need assistance, please contact Rochester International Airport (Rochester, MN) Customer Support as follows:
Email: rst@flyrst.com
Phone: 507.282.2328