RST Upgrade

RST is undertaking a $12 Million, 12 month Terminal construction project with Kraus-Anderson Construction breaking ground April 2017. The main terminal will remain operational throughout the duration of the project with updates to include:

  • Centralized ticketing counters
  • Consolidated baggage claim
  • Facility updates to extend life of the terminal building
  • Enhanced customer service experience
  • Requirements to retain US Customs as a Port of Entry

****************************************************************************************************************

  • 6/12/2017 Update: Baggage Claim operations are all currently consolidated to the baggage belt near the Delta Air Lines ticket counter (West end of terminal).  
  • 8/30/2017 Update: TSA Checkpoint work has commenced. Temporary walls are in place which have constricted the width of the checkpoint. Upon completion of the checkpoint work, anticipated November 2017, a dedicated TSA PreCheck lane will be available for passengers at RST.

September 2017 RST Construction Monthly

August 2017 RST Construction Monthly

July 2017 RST Construction Monthly

June 2017 RST Construction Monthly

May 2017 RST Construction Monthly

****************************************************************************************************************

See the full release: RST Upgrade release

Watch for updates on Facebook and Twitter and look for #RSTUpgrade to stay informed and learn more about this exciting project.